| Title | LS Cable & System and LS Marine Solution to Cooperate on KEPCO Submarine Cable Project, Strengthen Leadership in Korea’s Submarine Cable Market |
|---|---|
| Date | 2026-11-20 |

Photograph) LS Marine Solution’s cable-laying vessel GL2030 loads submarine cables manufactured by LS Cable & System at Donghae Port in Gangwon Province, Korea.
■ Third Hwawon–Anjwa contract since pioneering domestic production of extra-high-voltage submarine cables
■ Unrivaled track record in domestic public-sector submarine cable projects
■ New HVDC cable-laying vessel positions LS Marine Solution for Energy Highway projects
LS Cable & System and LS Marine Solution are expanding their cooperation on Korea Electric Power Corporation (KEPCO) submarine cable projects to strengthen their leadership in Korea’s submarine power grid market.
LS Cable & System announced on November 20 that it had been selected through a competitive tender for the second phase of KEPCO’s Hwawon–Anjwa submarine cable capacity expansion project.
The project will involve the installation of an additional 14 km of 154 kV extra-high-voltage submarine cables in the submarine power link built in 2010 between Hwawon-myeon in Haenam County and Anjwa Island in Shinan County, Jeollanam-do. This will support the development of renewable energy along Korea’s southwestern coast and increase the transmission capacity of the network.
LS Marine Solution’s 9,000-ton-class cable-laying vessel GL2030 will be deployed for the project, which is targeted for completion in December 2028.
The Hwawon–Anjwa submarine power link was LS Cable & System’s first project after the company became the first in Korea to develop and produce extra-high-voltage submarine cables domestically in 2009. The company also took part in the first capacity expansion project in 2021, making this its third contract for the same route.
LS Cable & System has an unrivaled track record of winning public-sector submarine cable contracts in Korea, and this latest project further demonstrates its technical expertise and project execution capabilities.
LS Marine Solution is upgrading its installation capabilities by building a 19,000-ton-class vessel for laying high-voltage direct current (HVDC) submarine cables, with deployment targeted for 2028. As the only Korean company to have commercialized HVDC submarine cables, LS Cable & System plans to draw on this experience and LS Marine Solution’s installation capabilities and pursue more national power grid projects, including the West Coast Energy Highway.
“For submarine cables, quality proven in real-world grid operation and experience in project execution are essential,” said a spokesperson for LS Cable & System. “We will strengthen our market leadership by combining the technical expertise we have built since pioneering domestic production with LS Marine Solution’s installation capabilities.”